implementation

Build the application

Inspect the original prompt language first, then copy or adapt it once you know how it fits your workflow.

Linked challenge: Build a Heat-Aware Steel Erection Shift Planner

Format
Code-aware
Lines
101
Sections
11
Linked challenge
Build a Heat-Aware Steel Erection Shift Planner

Prompt source

Original prompt text with formatting preserved for inspection.

101 lines
11 sections
No variables
1 code block
## Build
Evaluate ambient temperature, wind gusts, and thermal steel expansion to schedule structural steel lifting and bolt-torquing. Assemble safety-compliant work rosters to protect site rigging crews from extreme heat hazards.

## User
Site Structural Construction Superintendent

## Workflow
1. Ingest heavy structural lift manifests, crane lift radius capacities, and hourly microclimate heat forecasts.
2. Calculate thermal expansion allowances on critical long-span trusses to avoid alignment binding.
3. Apply wet-bulb globe temperature worker exposure thresholds to establish mandatory rest-work cycles.
4. Synthesize a daily steel erection shift plan scheduling heavy rigging during cool nocturnal and early dawn hours.

## Interface
Daily rigging board showing hourly crane wind limits, thermal expansion risk indicators, and crew work-rest rotations.

## Data
Synthesize structural lift lists with steel member lengths, weights, and forecasted 24-hour weather station feeds.
Starter examples below are synthetic. They are not downloaded records.

## Source
[EnergyPlus](https://raw.githubusercontent.com/NREL/EnergyPlus/develop/README.md)
Draws on EnergyPlus weather parsing and design-day thermal concepts to structure microclimate hourly ambient boundary inputs.

## Tools
agno, pydantic, fastapi.
Agno provides lightweight agent workflows for synthesizing complex shift schedules under multi-variable engineering constraints.
Hosted Claude API for evaluating trade-offs between crane availability and worker heat safety limits.

## Deliverables
Submit runnable source, pinned dependencies, setup commands, a working interface, example outputs, and a recorded end-to-end demo. Include tests and an action log.

## Acceptance
- Restricts heavy crane lifts when forecasted ambient temperatures exceed 44 degrees Celsius or wind exceeds safe boom speeds.
- Schedules high-precision structural bolt connections during hours where thermal expansion variance is below 3 mm.
- Produces an hourly rigging schedule with assigned mandatory shaded rest intervals.

## Starter Examples
```json
[
  {
    "input": {
      "lift_id": "LIFT-TRUSS-01",
      "truss_length_m": 42,
      "weight_tons": 18.5,
      "forecast": [
        {
          "hour": "04:00",
          "temp_c": 31,
          "wind_ms": 3.2
        },
        {
          "hour": "08:00",
          "temp_c": 38,
          "wind_ms": 5.1
        },
        {
          "hour": "12:00",
          "temp_c": 46,
          "wind_ms": 7.8
        }
      ]
    },
    "expected_output": {
      "approved_window": "04:00 - 07:00",
      "thermal_expansion_mm": 6.2,
      "work_rest_ratio": "50_10",
      "shift_status": "APPROVED_EARLY_DAWN",
      "prohibited_hours": [
        "11:00",
        "12:00",
        "13:00",
        "14:00",
        "15:00"
      ]
    }
  },
  {
    "input": {
      "lift_id": "LIFT-TRUSS-02",
      "truss_length_m": 20,
      "weight_tons": 8,
      "forecast": [
        {
          "hour": "04:00",
          "temp_c": 35,
          "wind_ms": 14.5
        },
        {
          "hour": "08:00",
          "temp_c": 42,
          "wind_ms": 12
        }
      ]
    },
    "expected_output": {
      "approved_window": "NONE",
      "thermal_expansion_mm": 4.1,
      "work_rest_ratio": "UNSAFE",
      "shift_status": "POSTPONED",
      "prohibited_hours": [
        "04:00",
        "08:00"
      ]
    }
  }
]
```

## Safety
Rigging plans are operational proposals; certified crane lift supervisors must conduct physical wind and rigging inspections prior to hoisting.
Use mock external writes. Require human review before any real deployment.

Adaptation plan

Keep the source stable, then change the prompt in a predictable order so the next run is easier to evaluate.

Keep stable

Hold the task contract and output shape stable so generated implementations remain comparable.

Tune next

Update libraries, interfaces, and environment assumptions to match the stack you actually run.

Verify after

Test failure handling, edge cases, and any code paths that depend on hidden context or secrets.